Verdrag van de Verenigde Naties inzake de overeenkomsten voor het internationaal vervoer van goederen geheel of gedeeltelijk over zee
1. A maritime performing party is subject to the obligations and liabilities imposed on the carrier under this Convention and is entitled to the carrier’s defences and limits of liability as provided for in this Convention if:
a) The maritime performing party received the goods for carriage in a Contracting State, or delivered them in a Contracting State, or performed its activities with respect to the goods in a port in a Contracting State; and
b) The occurrence that caused the loss, damage or delay took place: (i) during the period between the arrival of the goods at the port of loading of the ship and their departure from the port of discharge from the ship and either (ii) while the maritime performing party had custody of the goods or (iii) at any other time to the extent that it was participating in the performance of any of the activities contemplated by the contract of carriage.
2. If the carrier agrees to assume obligations other than those imposed on the carrier under this Convention, or agrees that the limits of its liability are higher than the limits specified under this Convention, a maritime performing party is not bound by this agreement unless it expressly agrees to accept such obligations or such higher limits.
3. A maritime performing party is liable for the breach of its obligations under this Convention caused by the acts or omissions of any person to which it has entrusted the performance of any of the carrier’s obligations under the contract of carriage under the conditions set out in paragraph 1 of this article.
4. Nothing in this Convention imposes liability on the master or crew of the ship or on an employee of the carrier or of a maritime performing party.
a) The maritime performing party received the goods for carriage in a Contracting State, or delivered them in a Contracting State, or performed its activities with respect to the goods in a port in a Contracting State; and
b) The occurrence that caused the loss, damage or delay took place: (i) during the period between the arrival of the goods at the port of loading of the ship and their departure from the port of discharge from the ship and either (ii) while the maritime performing party had custody of the goods or (iii) at any other time to the extent that it was participating in the performance of any of the activities contemplated by the contract of carriage.
2. If the carrier agrees to assume obligations other than those imposed on the carrier under this Convention, or agrees that the limits of its liability are higher than the limits specified under this Convention, a maritime performing party is not bound by this agreement unless it expressly agrees to accept such obligations or such higher limits.
3. A maritime performing party is liable for the breach of its obligations under this Convention caused by the acts or omissions of any person to which it has entrusted the performance of any of the carrier’s obligations under the contract of carriage under the conditions set out in paragraph 1 of this article.
4. Nothing in this Convention imposes liability on the master or crew of the ship or on an employee of the carrier or of a maritime performing party.