BWBV0001434
Geldig vanaf 18-06-2001
Artikel 9
Gezamenlijk Verdrag inzake de veiligheid van het beheer van bestraalde splijtstof en inzake de veiligheid van het beheer van radioactief afval
Each Contracting Party shall take the appropriate steps to ensure that:
(i) the licence to operate a spent fuel management facility is based upon appropriate assessments as specified in Article 8 and is conditional on the completion of a commissioning programme demonstrating that the facility, as constructed, is consistent with design and safety requirements;
(ii) operational limits and conditions derived from tests, operational experience and the assessments, as specified in Article 8, are defined and revised as necessary;
(iii) operation, maintenance, monitoring, inspection and testing of a spent fuel management facility are conducted in accordance with established procedures;
(iv) engineering and technical support in all safety-related fields are available throughout the operating lifetime of a spent fuel management facility;
(v) incidents significant to safety are reported in a timely manner by the holder of the licence to the regulatory body;
(vi) programmes to collect and analyse relevant operating experience are established and that the results are acted upon, where appropriate;
(vii) decommissioning plans for a spent fuel management facility are prepared and updated, as necessary, using information obtained during the operating lifetime of that facility, and are reviewed by the regulatory body.
(i) the licence to operate a spent fuel management facility is based upon appropriate assessments as specified in Article 8 and is conditional on the completion of a commissioning programme demonstrating that the facility, as constructed, is consistent with design and safety requirements;
(ii) operational limits and conditions derived from tests, operational experience and the assessments, as specified in Article 8, are defined and revised as necessary;
(iii) operation, maintenance, monitoring, inspection and testing of a spent fuel management facility are conducted in accordance with established procedures;
(iv) engineering and technical support in all safety-related fields are available throughout the operating lifetime of a spent fuel management facility;
(v) incidents significant to safety are reported in a timely manner by the holder of the licence to the regulatory body;
(vi) programmes to collect and analyse relevant operating experience are established and that the results are acted upon, where appropriate;
(vii) decommissioning plans for a spent fuel management facility are prepared and updated, as necessary, using information obtained during the operating lifetime of that facility, and are reviewed by the regulatory body.